Well 1 Vault Replacement Project CIPW13
In general the work consists of safety and operational improvements at the Well No. 1 vault. This includes replacement of the vault cover with a new traffic-rated OSHA compliant double access hatch. Replacement of the two existing sodium hypochlorite storage tanks with three new sodium hypochlorite storage tanks and the additional of a mixing tank inside the vault. Relocation of the existing chemical metering pump and power receptacle. Installation of a new forced-air ventilation system, as well as waterproofing of the interior vault.
Specifications
(click to expand/collapse)
Name | Size | ||
Notice to Bidders | 181.4 KB | ||
Vault Cover & Air Exchange Project-Final Revised-Specifications | 2.6 MB |